  1. Pump room
  2. Generator room
  3. Electrical room
  4. Fan rooms

The taller the building, the more technical rooms it has. These are the main technical rooms:

  1. A pump room and water reservoir (for drinking water and for firefighting), lower and upper.
  2. A generator room.
  3. An electrical room.
  4. Fan rooms.

Pump room

A water pump on a stainless steel base in the pump room, with a digital level lying on the base

The pump room is the most complex technical space in the building. In tall buildings, and especially in high-rises, the pump room includes:

  • Water pumps
  • An expansion tank
  • A water reservoir (which has to be completely watertight)
  • A float system
  • A control panel (ventilated)
  • A water supply piping system
  • A fire pump
  • A jockey pump
  • A fan to ventilate the room, or another means of ventilation
  • A firefighting piping system
  • A hydrant piping system

You can read about the building's water supply system on the page Plumbing and drainage systems.

Generator room

The generator's job is to run the essential systems in an emergency: the fire suppression system, smoke detection, the elevators, the water supply pumps and all the fans in the building.

The generator room needs a supply of fresh air in a suitable volume on one side, and a pipe for exhaust fumes on the other.

The electrical conduits and the electrical panel have to be installed in a safe, protected way.

The room has to be completely sealed against water penetration.

The diesel tank has to be accessible and full when the building is handed over.

We recommend checking the batteries' expiry at the time of handover.

Electrical room

The electrical room houses the building's main panels, and it receives the power from the Israel Electric Corporation.

Panels of more than 100 amps need a separate fire suppression system for each panel (in addition to the sprinkler system in the room).

The room needs a smoke detection system over every electrical panel.

The electrical panels have to be labeled.

Clearly the room has to be completely sealed against water penetration, but in practice that is not always the case.

The electrical conduits have to be installed in a safe, protected way.

The entrance door to the room has to be a fire door that is level and sealed against smoke. More on this on the page Electrical engineer inspection.

Fan rooms

Two green fans and sheet-metal ducts on the roof of a high-rise building

The fan rooms, which are usually spread around the underground parking garage, have to be accessible, with no parking spaces blocking them.

They have to be completely watertight.

Between metal parts connected to each other by a flexible section, electrical continuity by cable is required for grounding.

The fan space has to be roomy and lit so that it can be maintained. More than once we have found a fan room with no lighting installed.

The fan room needs an air intake louver of a suitable area.

The fan room has to be built so that the fan can push the smoke out without water getting in.

Sometimes a special room is built for the electrical panels and the fan controllers. This room too has to be completely watertight, so that the sensitive systems inside it are not damaged.

You can read about the role of the fans in an emergency on the page Life-saving systems.

The engineers of Arad Bedek Bayit, led by building engineer Ron Arad, whom courts appoint as their own expert on construction defects. The company has been inspecting apartments and buildings since 2001. Engineer Ron Arad · More about the company

Real reviews on Google

4.9 out of 5 · 55 reviews

  • Arad Bedek Bayit prepared an engineering expert opinion to our satisfaction and brought about success in our lawsuit against the contractor… Warmly recommended

    Sharon Elkayam · a claim against a contractor

  • Professional, thorough, and excellent service throughout the process. A must for every apartment buyer. Highly recommended

    Ef Ya · buying an apartment

  • …Contractors regard Arad's reports as reliable, so it is relatively very easy to deal with them when it comes to getting the defects handled. Highly recommended

    Shalom Maoz · building committee and private client

  • …He found several flaws I had not noticed and, most important, moisture in a kitchen cabinet caused by a poorly sealed water pipe…

    Yonatan Y · new apartment

  • After a thorough survey, and after going through sample reports from several inspection companies, I chose Arad Bedek Bayit…

    Orit Horowitz · compared reports

  • …Thanks to them we made several essential repairs in the apartment we bought, things we had not seen and did not know about…

    Reut Azriel-Ifergan · dampness and resale

  • The engineer arrived on time, checked the apartment down to the smallest detail and came across as very thorough… much more than just a report.

    Arnon Meiri · building inspection

  • …The real solution to dampness and mold problems is found only with engineers who examine things in depth, professionally and objectively.

    Y. Bril · dampness and mold

  • Arad carried out a comprehensive inspection of the apartment for us before we bought it. The engineer was very courteous and professional, explained everything…

    Michal Torky · before buying

More on this topic